Construction Updates

Your Annual Street Maintenance Program

 
The annual Street Resurfacing Program has begun on nearly 2.82 miles of your Mokena streets. Due to the volume of work involved in this project, this work should take roughly 8-10 weeks.

The program contains five typical sequential stages:

  1. Sawcutting of the curbs and sidewalks on your street:  Make the cuts in the curbs and sidewalks where the old concrete will be removed and replaced.
  2. Removal and replacement of the curbs and sidewalks:  The old concrete is removed and new concrete is poured in its place.
  3. Grinding of asphalt:  2" of the old asphalt is taken off the top of the street through a grinding process.
  4. Pavement patching:  Any spots in the street that need extra attention are patched.
  5. A final new layer of asphalt is placed.

Once the first step is started and/or completed on your roadway, it could be a week or longer before the next step gets started.  While you may experience some inconvenience during construction, resurfaced streets are a positive outcome once completed. 

Week of September 21st - Pavement patching will finish up this week, and weather depending, the contractor will begin laying the new layer of asphalt.

Below is a list of the streets that are part of this year's program, as well as a map.  Check back for updates on what work is being done in which areas.  Please contact us at (708) 479-3900 with any questions or concerns you may have about the program.  We appreciate your cooperation in improving our community!

Project Streets

Grasmere Subdivision

  • Kirkstone Way (south of 195th Street)
  • Bedford Ln
  • Lancaster Drive (south of 195th Street)
  • Trenton Way (south of 195th Street)
  • Stonehenge Drive (south of 195th Street)
  • Lindsay Lane
  • Royal Court
  • Cambridge Drive (west of Stonehenge Drive)
  • Derby Lane (west of Everett Lane)

Map of streets being resurfaced






















 

 

Annual Sidewalk Repair Program

Work on the annual sidewalk repair program is mostly complete.  Site restoration will take place over the next couple of weeks.

Please contact us at (708) 479-3900 with any questions or concerns you may have about the program.  We appreciate the opportunity to serve you!

Annual Street Patching Program

Work will be performed in various areas throughout the Village during the month of September.  This work consists of complete full-depth removal and hot mix asphalt replacement of areas in the roadway which have deteriorated.

If you have any questions or concerns about this program, please feel free to contact us at (708) 479-3900. 

 

Wolf Road PCC Pavement Patching Program

Work continues on the Wolf Road PCC Pavement Patching program. Cracked and deteriorated pavement will be replaced in multiple areas.

Two-way traffic control will be maintained, but intermittent lane closures are expected.  Please watch for signs and flaggers, and maintain a lower speed through construction zones.  Construction is anticipated to be completed by October 1st.

If you have any questions or concerns, please feel free to contact us at (708) 479-3900.  We thank you in advance for your patience and understanding as we work to improve your Mokena streets.


Updated September 21, 2020

     
     
     

     
    Village of Mokena | 11004 Carpenter Street Mokena, IL 60448
    Phone: (708) 479-3900  |  Fax: (708) 479-4844
    Contact Us  |  Site Map   |  Powered by MunicipalCMS
    E-notify RSS Feeds 
     
    0